Float, the critical path and the value of network analysis
- 5 things to know
- Papers 1, 2 and 3
Overview
Calculating total float, identifying the critical path, and what network analysis is used for.
What you need to know
Answer each one before you reveal it.
What is total float, what happens when an activity with float is delayed, and how does network analysis track progress?
What are network diagrams for, what is the critical path, and how is it identified?
When is total float calculated, and how does structure affect implementation?
State the formula for calculating total float.
Questions from this subtopic
Each one with the model answer underneath.
- 1
What is the float value for activities on the critical path, and what does this mean?
Model answer
Activities on the critical path have zero float, meaning any delay to these activities will delay the entire project.
- 2
Define total float in the context of network analysis.
Model answer
Total float is the amount of time an activity can be delayed without delaying the overall project completion date.
- 3
State the formula for calculating total float.
Model answer
Total Float = Latest Start Time − Earliest Start Time (or Latest Finish Time − Earliest Finish Time).
- 4
What do the terms 'earliest start time' and 'latest start time' mean in the total float formula?
Model answer
Earliest start time is the soonest an activity can begin based on predecessor completion; latest start time is the latest it can begin without delaying the project.
- 5
Calculate the total float when earliest start time = 46 days, latest start time = 52 days.
Model answer
Total float = 52 - 46 = 6 days.
- 6
Why is identifying the critical path valuable for managers during strategic implementation?
Model answer
It allows managers to focus resources and attention on activities where delays would be most damaging to project completion.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Managing Strategic Change, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.