Network analysis and reading a network diagram
- 2 things to know
- Papers 1, 2 and 3
Overview
What a network diagram shows, how activities are represented, and how it is amended.
What you need to know
Answer each one before you reveal it.
What is the critical path, what float do its activities have, and why is identifying it valuable?
Questions from this subtopic
Each one with the model answer underneath.
- 1
Define network analysis as a project management technique.
Model answer
Network analysis is a project management technique that identifies the sequence of activities, their dependencies, and the minimum time required to complete a project.
- 2
What is a network diagram?
Model answer
A network diagram visually represents project activities as nodes or arrows, showing the sequence and dependencies between tasks.
- 3
How are activities represented in network diagrams?
Model answer
Activities are represented with their duration, and arrows or nodes show the logical sequence in which activities must be completed.
- 4
When interpreting a network diagram, how do you identify predecessor activities?
Model answer
By examining the arrows or connections leading into each activity node, which show which tasks must be completed before that activity can begin.
- 5
What does calculating time for different paths through a network diagram involve?
Model answer
It involves adding up the durations of all activities along each possible route from start to finish to determine how long each path takes.
- 6
How would you amend a network diagram when an activity's duration changes?
Model answer
Update the duration shown for that activity and recalculate the times for all subsequent activities and paths affected by the change.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Managing Strategic Change, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.