  • 1 thing to know
  • Component 03

Overview

Recall questions on total float and free float, how each is calculated and how they differ, float on the critical path, the effect of delays on completion, and using a network to manage resources and project cash flow.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

What is total float?

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    What is total float?

    Model answer

    Total float is the amount of time an activity can be delayed without delaying the completion of the whole project.

  2. 2

    State the formula for total float.

    Model answer

    Total float equals the latest finish time minus the activity's duration minus its earliest start time.

  3. 3

    What is free float?

    Model answer

    Free float is the amount of time an activity can be delayed without delaying the earliest start time of the activity that follows it.

  4. 4

    State how free float is calculated.

    Model answer

    Subtract the activity's duration and its earliest start time from the earliest start time of the following activity.

  5. 5

    An activity has an earliest start time of day 12, a duration of 5 days and a latest finish time of day 20. Calculate its total float.

    Model answer

    Total float is 20 − 5 − 12 = 3 days.

  6. 6

    An activity has an earliest start time of day 8 and a duration of 4 days, and the activity following it has an earliest start time of day 15. Calculate its free float.

    Model answer

    Free float is 15 − 4 − 8 = 3 days.

Other ways to work this

The same content, four other ways.

What is inside Levo

Six ways to work the same material.

1Closed book
2Open book
3Closed book

The 3-step method, run for you

Answer cold, learn it, then prove it stuck. Levo tracks the jump between your first attempt and your last.

Business Activity
Marketing
People
Operations

Cram a whole paper in one sitting

Sort every topic into what you know and what you do not, then drill only the weak ones.

The Policy Committee.
MonetaryFiscalBudget

Blank Blitz makes facts automatic

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

AContribution per unit falls.
BMany more units must be sold to cover fixed costs.
CCash inflows can drop before the extra volume arrives.

Build It gets the exam shape right

Assemble a full-mark answer from its marking points, in the order an examiner wants them.

Responsibility means the duty to carry out a task that has been given to you.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The traps are the mistakes students actually make.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Strategy, Risk and Managing Change, on a schedule.

Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.