CCEA A-Level Professional Business Services 3210
The Business Environment
The Professional Business Services Sector
The Consultancy Process
Understanding the Client's Market
Client Relationships
Business Ethics
Persuading, Negotiating and Influencing
Business Planning and Risk Management
Government Regulation
Organisational Structure and Culture
Recruitment and Selection
Learning and Development
Employee Well-Being and Motivation
Managing Conflict
Business Research Methods
Sources of Finance
Cash Flow
Financial Statements
Ratio Analysis
Investment Appraisal and Financial Decisions
IT Systems and Communication Technology
Technology for People and Operations
Technology for Finance and Disaster Recovery
Big Data and the Ethics of Technology
Leadership and Management
Managing Teams
Managing Change
Project Management and Feasibility
Project Initiation and Planning
Project Initiation and Planning
Project tolerances for time, cost, quality and risk
- 3 things to know
- A2 3
Overview
Time, cost, quality and risk tolerances, worked cost tolerance and escalation calculations, exceptions and management by exception, and setting tolerances well.
What you need to know
Answer each one before you reveal it.
What is a project tolerance?
Name four areas in which tolerances are set.
Questions from this subtopic
Each one with the model answer underneath.
- 1
What is a project tolerance?
Model answer
A tolerance is the permitted deviation from a plan before the matter must be referred upward. A tolerance of two weeks, for example, lets a project finish up to two weeks late.
- 2
Name four areas in which tolerances are set.
Model answer
Tolerances are commonly set for time, cost, quality and risk. Scope and benefits can also carry tolerances.
- 3
Why are tolerances set for a project?
Model answer
Tolerances let the project manager deal with small variations without going to the board. The board is only involved when a deviation is serious.
- 4
What is a time tolerance?
Model answer
A time tolerance is the delay allowed against the planned completion date. A project with a one-month tolerance can finish up to a month late without escalation.
- 5
What is a cost tolerance?
Model answer
A cost tolerance is the overspend or underspend allowed against the budget. The tolerance is often stated as a percentage of the budget.
- 6
A project has a budget of £80,000 and a cost tolerance of plus or minus 10%. What spending range is allowed?
Model answer
Spending between £72,000 and £88,000 is allowed. The working is 10% of £80,000 = £8,000, so £80,000 ± £8,000.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Project Initiation and Planning, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.