CCEA A-Level Professional Business Services 3210
The Business Environment
The Professional Business Services Sector
The Consultancy Process
Understanding the Client's Market
Client Relationships
Business Ethics
Persuading, Negotiating and Influencing
Business Planning and Risk Management
Government Regulation
Organisational Structure and Culture
Recruitment and Selection
Learning and Development
Employee Well-Being and Motivation
Managing Conflict
Business Research Methods
Sources of Finance
Cash Flow
Financial Statements
Ratio Analysis
Investment Appraisal and Financial Decisions
IT Systems and Communication Technology
Technology for People and Operations
Technology for Finance and Disaster Recovery
Big Data and the Ethics of Technology
Leadership and Management
Managing Teams
Managing Change
Project Management and Feasibility
Project Initiation and Planning
Project Management and Feasibility
Project documents, plans and registers
- 3 things to know
- A2 3
Overview
The business case, project brief, PID, progress and closure reports, project plans, and risk, issues and lessons learned registers.
What you need to know
Answer each one before you reveal it.
What is the purpose of a business case?
What is the purpose of a project brief?
Questions from this subtopic
Each one with the model answer underneath.
- 1
Name the main documents used in project management.
Model answer
The main documents are the business case, project brief, project initiation document, project progress report and project closure report. Plans and registers are also kept, such as the risk register.
- 2
What is the purpose of a business case?
Model answer
A business case justifies a project by weighing its expected benefits against its costs and risks. The board uses it to decide whether the project is worth starting.
- 3
What is the purpose of a project brief?
Model answer
A project brief gives a short outline of the project's background, scope and objectives. The brief is the starting point for detailed planning.
- 4
What is a project initiation document (PID)?
Model answer
A PID is the full, agreed definition of the project, drawn up at initiation. The PID sets out objectives, scope, roles, plans, costs, risks and controls.
- 5
What is a project progress report?
Model answer
A progress report updates the board on what has been completed against the plan. The report also covers spending, risks, issues and the next steps.
- 6
What is a project closure report?
Model answer
A closure report records whether the project met its objectives, budget and deadline. The report confirms handover of the deliverables and lists lessons learned.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Project Management and Feasibility, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.