CCEA A-Level Professional Business Services 3210
The Business Environment
The Professional Business Services Sector
The Consultancy Process
Understanding the Client's Market
Client Relationships
Business Ethics
Persuading, Negotiating and Influencing
Business Planning and Risk Management
Government Regulation
Organisational Structure and Culture
Recruitment and Selection
Learning and Development
Employee Well-Being and Motivation
Managing Conflict
Business Research Methods
Sources of Finance
Cash Flow
Financial Statements
Ratio Analysis
Investment Appraisal and Financial Decisions
IT Systems and Communication Technology
Technology for People and Operations
Technology for Finance and Disaster Recovery
Big Data and the Ethics of Technology
Leadership and Management
Managing Teams
Managing Change
Project Management and Feasibility
Project Initiation and Planning
Project Initiation and Planning
The initiation stage and the project initiation document
- 3 things to know
- A2 3
Overview
Why initiation matters, the decisions it involves, the contents and approval of the PID, communication plans, scope creep, client sign-off and stakeholder analysis.
What you need to know
Answer each one before you reveal it.
Why is the initiation stage important in project management?
What decisions are made at the initiation stage?
Questions from this subtopic
Each one with the model answer underneath.
- 1
Why is the initiation stage important in project management?
Model answer
The initiation stage confirms that the project is worth doing and defines exactly what it will deliver. A weak start leads to confusion, scope creep and wasted money later.
- 2
What decisions are made at the initiation stage?
Model answer
The project board decides whether to authorise the project. The board also approves its objectives, scope, budget, timescale and the people in each role.
- 3
Why does the PID matter so much during initiation?
Model answer
The PID records the agreed definition of the project in one approved document. The PID becomes the reference against which every later decision and change is judged.
- 4
What are the main contents of a PID?
Model answer
A PID contains the background, objectives, scope, deliverables, business case, roles, plans, risks, tolerances and controls. The PID also sets out how the project will communicate with stakeholders.
- 5
Who approves the PID?
Model answer
The project board approves the PID. Approval gives the project manager authority to begin detailed planning and work.
- 6
Why does the PID include a communication plan?
Model answer
A communication plan states who receives which information, how and how often. Stakeholders then stay informed and problems are raised early.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Project Initiation and Planning, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.