Stock control diagrams and stock levels

  • 3 things to know
  • Component 1

Overview

Maximum stock level, re-order level and lead time.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

What does a stock control diagram show?

Key term

What is the maximum stock level?

Key term

What is the re-order level?

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    What does a stock control diagram show?

    Model answer

    A stock control diagram plots the level of stock held against time. Sawtooth lines show stock falling as it is used and jumping when a delivery arrives.

  2. 2

    What is the maximum stock level?

    Model answer

    The maximum stock level is the largest quantity a business is willing to hold. Storage space, cost and the risk of deterioration set that limit.

  3. 3

    What is the re-order level?

    Model answer

    The re-order level is the stock level at which a fresh order is placed. The level is set high enough to cover usage during the lead time.

  4. 4

    What is lead time?

    Model answer

    Lead time is the period between placing an order and receiving the delivery. A longer lead time forces a higher re-order level.

  5. 5

    What is buffer stock?

    Model answer

    Buffer stock is the minimum level a business plans never to go below. The reserve protects production against a late delivery or a surge in demand.

  6. 6

    What is the re-order quantity?

    Model answer

    The re-order quantity is the amount ordered each time stock reaches the re-order level. Larger orders earn bigger discounts but raise the cost of holding stock.

Other ways to work this

The same content, four other ways.

What is inside Levo

Six ways to work the same material.

1Closed book
2Open book
3Closed book

See a huge jump in your memorisation

Answer cold, learn it, then prove it stuck. Levo tracks the jump between your first attempt and your last.

Enterprise, Business Plans and Location
Markets, Demand and Market Research
Business Structure and Sources of Finance
Revenue, Costs and Break-Even

Cram a whole paper in one sitting

Sort every topic into what you know and what you do not, then drill only the weak ones.

£240,000 by £120,000 gives 2.
dividedmultipliedadded

Blank Blitz consolidates the facts

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

ASoftware produces a result from whatever data it is given.
BPoor data produces a confident but wrong answer.
CSystems are also costly to buy, maintain and staff.

Build It trains answer structure

Assemble a full-mark answer from its marking points, in the order an examiner wants them.

Capacity is the maximum output possible.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The traps are the mistakes students actually make.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Operations Management, on a schedule.

Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.