Managing Projects

Float and how it is used

  • 3 things to know
  • A2 Unit 1

Overview

Two equivalent ways of calculating total float, free float and float on an activity that lies on the critical path.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

What does negative float mean?

Key term

An activity can start no earlier than day 5 and no later than day 7. State its total float.

Key term

Define free float.

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    What is float?

    Model answer

    Float is the amount of time an activity can be delayed without causing a delay somewhere that matters, and it exists because a chain of activities is shorter than the critical chain running beside it.

  2. 2

    State two equivalent ways of calculating total float.

    Model answer

    Total float is the latest start minus the earliest start, and it is equally the latest finish minus the earliest finish, because both subtractions measure the same slack in the activity's window.

  3. 3

    An activity can start no earlier than day 5 and no later than day 7. State its total float.

    Model answer

    The total float is 7 − 5 = 2 days, so the activity may begin up to 2 days late without pushing the project's end date.

  4. 4

    An activity has an earliest finish of day 8 and a latest finish of day 10. State its total float and explain what a delay of 3 days would do.

    Model answer

    The total float is 10 − 8 = 2 days, so a delay of 3 days exceeds the float by 1 day and the project finishes 1 day late.

  5. 5

    Define free float.

    Model answer

    Free float is the time an activity can be delayed without delaying the earliest start of any activity that immediately follows it.

  6. 6

    Activity C finishes at the earliest on day 8, and the activity that follows it can start at the earliest on day 8. State the free float of C.

    Model answer

    The free float of C is 8 − 8 = 0 days, so any delay to C immediately pushes back the earliest start of the activity after it.

Other ways to work this

The same content, four other ways.

What is inside Levo

Six ways to work the same material.

1Closed book
2Open book
3Closed book

The 3-step method, run for you

Answer cold, learn it, then prove it stuck. Levo tracks the jump between your first attempt and your last.

Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures

Cram a whole paper in one sitting

Sort every topic into what you know and what you do not, then drill only the weak ones.

A null is the of one.
absencepresencetype

Blank Blitz makes facts automatic

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

AA null means no value has been recorded.
BZero and an empty string are values.
CA null is the absence of a value.

Build It gets the exam shape right

Assemble a full-mark answer from its marking points, in the order an examiner wants them.

An error is the mistake a person made.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The traps are the mistakes students actually make.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Managing Projects, on a schedule.

Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.