CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Project Management and the Systems Approach in Practice
Breaking a development into tasks and deliverables
- 3 things to know
- A2 Unit 2
Overview
Deliverable in a development plan, term scope and one advantage of numbering the tasks in a project plan.
What you need to know
Answer each one before you reveal it.
What is the first thing a developer does when turning an agreed business problem into a project plan?
How does a work breakdown structure help when planning a database-driven desktop solution?
Questions from this subtopic
Each one with the model answer underneath.
- 1
What is the first thing a developer does when turning an agreed business problem into a project plan?
Model answer
The developer breaks the whole development into separate tasks, each of which produces something identifiable.
- 2
How does a work breakdown structure help when planning a database-driven desktop solution?
Model answer
A work breakdown structure splits the development into smaller and smaller pieces. Each piece ends up small enough for one person to estimate and finish.
- 3
What makes a task in a project plan too large to be useful?
Model answer
A task is too large when progress inside it cannot be judged, so the plan reports the same task as in progress for weeks.
- 4
Besides its name, give two things every task in a project plan should state.
Model answer
Every task should state its expected duration and the person responsible for carrying it out.
- 5
Define a deliverable in a development plan.
Model answer
A deliverable is a tangible product of a task, such as an agreed requirements document, an ER diagram or a working form.
- 6
Why is each task given a completion criterion?
Model answer
A completion criterion states what must exist before the task counts as finished. Progress cannot then be claimed on work that is still open.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Project Management and the Systems Approach in Practice, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.