CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Project Management and the Systems Approach in Practice
Milestones, reviews and user sign-off points
- 3 things to know
- A2 Unit 2
Overview
Milestone in a development plan, three sensible milestones for a database-driven desktop development and milestone and a deliverable.
What you need to know
Answer each one before you reveal it.
Why is a milestone given no duration?
Name three sensible milestones for a database-driven desktop development.
Questions from this subtopic
Each one with the model answer underneath.
- 1
Define a milestone in a development plan.
Model answer
A milestone is a dated point in the plan marking that a significant piece of work is complete.
- 2
Why is a milestone given no duration?
Model answer
A milestone marks an event rather than work, so no working time is allocated to it.
- 3
Name three sensible milestones for a database-driven desktop development.
Model answer
Sensible milestones are the requirements agreed, the design signed off and the solution accepted by the user.
- 4
How does a milestone let slippage be detected early?
Model answer
Comparing the date a milestone is actually reached with its planned date exposes slippage long before the final deadline.
- 5
Explain what a review point in a plan is for.
Model answer
A review point is a scheduled meeting at which finished work is checked with the user before the next stage begins.
- 6
Why is user sign-off scheduled at the end of the design stage?
Model answer
Sign-off confirms the user agrees the design before coding starts, while changes are still cheap to make.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Project Management and the Systems Approach in Practice, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.