CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Project Management and the Systems Approach in Practice
Building a plan capable of reflecting change
- 3 things to know
- A2 Unit 2
Overview
Baseline plan, rolling wave plan and scope creep.
What you need to know
Answer each one before you reveal it.
Why is a plan drawn up at the start certain to need changing?
How does keeping tasks short make a plan easier to change?
Questions from this subtopic
Each one with the model answer underneath.
- 1
What does it mean for a project plan to be capable of reflecting change?
Model answer
A plan capable of reflecting change can have its tasks, dates and dependencies revised as the development progresses. The whole plan does not have to be rewritten.
- 2
Why is a plan drawn up at the start certain to need changing?
Model answer
Estimates are made before the work is understood, and user requirements are refined as the development progresses.
- 3
How does keeping tasks short make a plan easier to change?
Model answer
Short tasks localise a delay to a few days, so a slipped task is re-scheduled without disturbing whole stages.
- 4
Define a baseline plan.
Model answer
A baseline plan is the version agreed at the start, kept unchanged so that later versions can be compared against it.
- 5
Why is the baseline kept once the plan starts changing?
Model answer
The baseline is the only record of what was originally promised, so variance can be measured against something fixed.
- 6
Where is contingency best placed in a plan that expects change?
Model answer
Contingency is best placed at the end of each stage rather than hidden inside individual tasks, so the spare time stays visible.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Project Management and the Systems Approach in Practice, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.