Managing Projects

Gantt charts and the schedule

  • 3 things to know
  • A2 Unit 1

Overview

Tracking Gantt chart and weakness of a Gantt chart as a planning tool.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

On a Gantt chart, what does the vertical line marking today's date tell a manager when compared with the shading?

Key term

How are dependencies represented on a Gantt chart?

Key term

How is a summary bar used on a Gantt chart?

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    What does a Gantt chart show?

    Model answer

    A Gantt chart lists the activities down the left-hand side against a calendar across the top, drawing each activity as a horizontal bar whose position gives its start and whose length gives its duration.

  2. 2

    How are dependencies represented on a Gantt chart?

    Model answer

    Dependencies are drawn as arrows running from the end of one bar to the start of another, showing that the second activity cannot begin until the first has finished.

  3. 3

    What does it mean when two bars on a Gantt chart cover the same weeks?

    Model answer

    Two bars covering the same weeks mean the activities are planned to run in parallel. Parallel working is only possible where the two activities do not depend on each other and the resources for both are available at once.

  4. 4

    How is a summary bar used on a Gantt chart?

    Model answer

    A summary bar spans all the detailed activities of one stage on a single line, so a manager can collapse the chart to the stage level for reporting and expand only the stage under discussion.

  5. 5

    How is progress recorded on a Gantt chart while work is under way?

    Model answer

    Progress is recorded by shading each bar in proportion to the part of the activity completed, so the shaded portion can be compared with where the current date falls.

  6. 6

    What does the vertical line marking today's date tell a manager when compared with the shading?

    Model answer

    An activity whose shading has not reached the vertical line for today is behind plan, and one shaded past it is ahead, which lets slippage be spotted at a glance across the whole project.

Other ways to work this

The same content, four other ways.

What is inside Levo

Six ways to work the same material.

1Closed book
2Open book
3Closed book

The 3-step method, run for you

Answer cold, learn it, then prove it stuck. Levo tracks the jump between your first attempt and your last.

Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures

Cram a whole paper in one sitting

Sort every topic into what you know and what you do not, then drill only the weak ones.

A null is the of one.
absencepresencetype

Blank Blitz makes facts automatic

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

AA null means no value has been recorded.
BZero and an empty string are values.
CA null is the absence of a value.

Build It gets the exam shape right

Assemble a full-mark answer from its marking points, in the order an examiner wants them.

An error is the mistake a person made.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The traps are the mistakes students actually make.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Managing Projects, on a schedule.

Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.