CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Managing Projects
Gantt charts and the schedule
- 3 things to know
- A2 Unit 1
Overview
Tracking Gantt chart and weakness of a Gantt chart as a planning tool.
What you need to know
Answer each one before you reveal it.
How are dependencies represented on a Gantt chart?
How is a summary bar used on a Gantt chart?
Questions from this subtopic
Each one with the model answer underneath.
- 1
What does a Gantt chart show?
Model answer
A Gantt chart lists the activities down the left-hand side against a calendar across the top, drawing each activity as a horizontal bar whose position gives its start and whose length gives its duration.
- 2
How are dependencies represented on a Gantt chart?
Model answer
Dependencies are drawn as arrows running from the end of one bar to the start of another, showing that the second activity cannot begin until the first has finished.
- 3
What does it mean when two bars on a Gantt chart cover the same weeks?
Model answer
Two bars covering the same weeks mean the activities are planned to run in parallel. Parallel working is only possible where the two activities do not depend on each other and the resources for both are available at once.
- 4
How is a summary bar used on a Gantt chart?
Model answer
A summary bar spans all the detailed activities of one stage on a single line, so a manager can collapse the chart to the stage level for reporting and expand only the stage under discussion.
- 5
How is progress recorded on a Gantt chart while work is under way?
Model answer
Progress is recorded by shading each bar in proportion to the part of the activity completed, so the shaded portion can be compared with where the current date falls.
- 6
What does the vertical line marking today's date tell a manager when compared with the shading?
Model answer
An activity whose shading has not reached the vertical line for today is behind plan, and one shaded past it is ahead, which lets slippage be spotted at a glance across the whole project.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Managing Projects, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.