Project Management and the Systems Approach in Practice

Updating the plan to reflect slippage

  • 3 things to know
  • A2 Unit 2

Overview

What crashing a plan means, what fast tracking a plan involves and recorded every time the plan is changed.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

Which three things does the developer update when a task overruns?

Key term

Why must the plan be updated as soon as slippage is known?

Key term

A task with six days of float slips by two days. What happens to the finish date?

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    Which three things does the developer update when a task overruns?

    Model answer

    The actual duration of the task, the dates of the tasks depending on it, and the critical path are all updated.

  2. 2

    Why must the plan be updated as soon as slippage is known?

    Model answer

    An out-of-date plan misleads everyone about the delivery date and hides the need for a decision.

  3. 3

    A task on the critical path slips by four days and nothing else changes. What happens to the planned finish date?

    Model answer

    The planned finish date moves back by four days, because every day lost on the critical path is lost from the whole development.

  4. 4

    A task with six days of float slips by two days. What happens to the finish date?

    Model answer

    The finish date does not move, because the two lost days are absorbed by the float and four days of float remain.

  5. 5

    Explain what crashing a plan means.

    Model answer

    Crashing a plan means shortening a critical task by adding resources to it, accepting extra cost in order to save time.

  6. 6

    Describe what fast tracking a plan involves.

    Model answer

    Fast tracking means starting a task before the task it depends on has completely finished, accepting the risk of rework.

Other ways to work this

The same content, four other ways.

What is inside Levo

Six ways to work the same material.

1Closed book
2Open book
3Closed book

The 3-step method, run for you

Answer cold, learn it, then prove it stuck. Levo tracks the jump between your first attempt and your last.

Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures

Cram a whole paper in one sitting

Sort every topic into what you know and what you do not, then drill only the weak ones.

A null is the of one.
absencepresencetype

Blank Blitz makes facts automatic

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

AA null means no value has been recorded.
BZero and an empty string are values.
CA null is the absence of a value.

Build It gets the exam shape right

Assemble a full-mark answer from its marking points, in the order an examiner wants them.

An error is the mistake a person made.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The traps are the mistakes students actually make.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Project Management and the Systems Approach in Practice, on a schedule.

Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.