CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Project Management and the Systems Approach in Practice
Updating the plan to reflect slippage
- 3 things to know
- A2 Unit 2
Overview
What crashing a plan means, what fast tracking a plan involves and recorded every time the plan is changed.
What you need to know
Answer each one before you reveal it.
Why must the plan be updated as soon as slippage is known?
A task with six days of float slips by two days. What happens to the finish date?
Questions from this subtopic
Each one with the model answer underneath.
- 1
Which three things does the developer update when a task overruns?
Model answer
The actual duration of the task, the dates of the tasks depending on it, and the critical path are all updated.
- 2
Why must the plan be updated as soon as slippage is known?
Model answer
An out-of-date plan misleads everyone about the delivery date and hides the need for a decision.
- 3
A task on the critical path slips by four days and nothing else changes. What happens to the planned finish date?
Model answer
The planned finish date moves back by four days, because every day lost on the critical path is lost from the whole development.
- 4
A task with six days of float slips by two days. What happens to the finish date?
Model answer
The finish date does not move, because the two lost days are absorbed by the float and four days of float remain.
- 5
Explain what crashing a plan means.
Model answer
Crashing a plan means shortening a critical task by adding resources to it, accepting extra cost in order to save time.
- 6
Describe what fast tracking a plan involves.
Model answer
Fast tracking means starting a task before the task it depends on has completely finished, accepting the risk of rework.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Project Management and the Systems Approach in Practice, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.