CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Managing Projects
Milestones and checkpoints
- 3 things to know
- A2 Unit 1
Overview
Milestone in a project plan, four milestones you would expect in a development plan and how milestones let slippage be detected early.
What you need to know
Answer each one before you reveal it.
Why does a milestone occupy no time on the schedule?
How should a milestone be worded, and why?
Questions from this subtopic
Each one with the model answer underneath.
- 1
What is a milestone in a project plan?
Model answer
A milestone is a significant point in the project that is either reached or not reached, such as the requirements being signed off or the system being installed for acceptance testing.
- 2
Why does a milestone occupy no time on the schedule?
Model answer
A milestone marks an event rather than a piece of work, so it consumes no effort and no duration; the work that leads up to it is what carries the time.
- 3
How should a milestone be worded, and why?
Model answer
A milestone is worded as a completed state rather than an activity, so 'test plan approved' rather than 'approve the test plan', because a state can be judged true or false while an activity can always be claimed to be under way.
- 4
Name four milestones you would expect in a development plan.
Model answer
Requirements signed off, design approved, code complete and passed to test, and acceptance testing passed are four milestones you would expect in a development plan.
- 5
Explain how milestones let slippage be detected early.
Model answer
Milestones spread across the project give a small number of unambiguous dates, so a milestone missed in month two is a warning about the whole plan long before the final deadline arrives.
- 6
Why is it dangerous to have only one milestone, at the end?
Model answer
A single milestone at the end gives no early warning at all, because progress until then rests on the team's own claims about percentage complete, and those claims can be wrong for months.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Managing Projects, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.