Milestones and checkpoints

  • 3 things to know
  • A2 Unit 1

Overview

Milestone in a project plan, four milestones you would expect in a development plan and how milestones let slippage be detected early.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

Why are payments to an external supplier often tied to milestones?

Key term

Why does a milestone occupy no time on the schedule?

Key term

How should a milestone be worded, and why?

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    What is a milestone in a project plan?

    Model answer

    A milestone is a significant point in the project that is either reached or not reached, such as the requirements being signed off or the system being installed for acceptance testing.

  2. 2

    Why does a milestone occupy no time on the schedule?

    Model answer

    A milestone marks an event rather than a piece of work, so it consumes no effort and no duration; the work that leads up to it is what carries the time.

  3. 3

    How should a milestone be worded, and why?

    Model answer

    A milestone is worded as a completed state rather than an activity, so 'test plan approved' rather than 'approve the test plan', because a state can be judged true or false while an activity can always be claimed to be under way.

  4. 4

    Name four milestones you would expect in a development plan.

    Model answer

    Requirements signed off, design approved, code complete and passed to test, and acceptance testing passed are four milestones you would expect in a development plan.

  5. 5

    Explain how milestones let slippage be detected early.

    Model answer

    Milestones spread across the project give a small number of unambiguous dates, so a milestone missed in month two is a warning about the whole plan long before the final deadline arrives.

  6. 6

    Why is it dangerous to have only one milestone, at the end?

    Model answer

    A single milestone at the end gives no early warning at all, because progress until then rests on the team's own claims about percentage complete, and those claims can be wrong for months.

Other ways to work this

The same content, four other ways.

What is inside Levo

Six ways to work the same material.

1Closed book
2Open book
3Closed book

The 3-step method, run for you

Answer cold, learn it, then prove it stuck. Levo tracks the jump between your first attempt and your last.

Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures

Cram a whole paper in one sitting

Sort every topic into what you know and what you do not, then drill only the weak ones.

A null is the of one.
absencepresencetype

Blank Blitz makes facts automatic

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

AA null means no value has been recorded.
BZero and an empty string are values.
CA null is the absence of a value.

Build It gets the exam shape right

Assemble a full-mark answer from its marking points, in the order an examiner wants them.

An error is the mistake a person made.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The traps are the mistakes students actually make.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Managing Projects, on a schedule.

Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.