CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Managing Projects
Network diagrams and PERT
- 3 things to know
- A2 Unit 1
Overview
Drawing tasks and their dependencies as a network, the forward and backward pass, earliest and latest start and finish, and the three-point estimate that averages optimistic, likely and pessimistic times.
What you need to know
Answer each one before you reveal it.
What does a network diagram show that a bar chart does not?
Describe the activity-on-node form of a network diagram.
Questions from this subtopic
Each one with the model answer underneath.
- 1
What does a network diagram show that a bar chart does not?
Model answer
A network diagram shows the logical dependencies between activities as a connected structure, so the chains running through the project and the longest of those chains can be identified.
- 2
Describe the activity-on-node form of a network diagram.
Model answer
In the activity-on-node form each activity is drawn as a box carrying its name, duration and calculated dates, and the arrows between boxes carry only the dependencies.
- 3
How does the activity-on-arrow form differ, and what is a dummy activity?
Model answer
In the activity-on-arrow form the arrows are the activities and the circles are events at their ends, and a dummy activity is a dotted arrow of zero duration used to express a dependency that the layout could not otherwise show.
- 4
What does a forward pass through a network calculate?
Model answer
A forward pass works from the start to the end of the network calculating the earliest start and earliest finish of every activity, and the largest earliest finish gives the shortest possible duration for the whole project.
- 5
When an activity has two predecessors, how is its earliest start found?
Model answer
An activity with two predecessors takes the later of their earliest finish times as its earliest start, because the activity cannot begin until both of the things it depends on are done.
- 6
What does a backward pass calculate, and where does it begin?
Model answer
A backward pass begins at the project end date and works towards the start, calculating the latest finish and latest start of each activity, meaning the last moment it could happen without delaying the project.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Managing Projects, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.