CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Project Management and the Systems Approach in Practice
Planning people, resources and skills
- 3 things to know
- A2 Unit 2
Overview
Resource levelling and what is meant by a resource constraint.
What you need to know
Answer each one before you reveal it.
Why is access to the user treated as a scheduled resource?
Define resource levelling.
Questions from this subtopic
Each one with the model answer underneath.
- 1
Which resources besides people have to be planned for a desktop development?
Model answer
The plan must allow for development machines, the database software, the development environment and access to the user.
- 2
Why is access to the user treated as a scheduled resource?
Model answer
The user is available only at agreed times, so interviews and reviews must be booked into the plan around that availability.
- 3
Define resource levelling.
Model answer
Resource levelling means rescheduling tasks, moving the finish date if necessary, so that no period demands more resource than is actually available; moving tasks only within their float is resource smoothing.
- 4
How would you plan for a technique the developer has not used before?
Model answer
The plan carries a separate learning task before the work that needs the technique, with realistic time allowed for it.
- 5
State one risk of scheduling two tasks that need the same machine at the same time.
Model answer
Two tasks needing one machine cannot both proceed, so one of them is delayed and the schedule becomes unachievable.
- 6
How does a plan record who is responsible for each task?
Model answer
Each task row names one owner, so responsibility for doing the work and for reporting progress is unambiguous.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Project Management and the Systems Approach in Practice, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.