CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Project Management and the Systems Approach in Practice
Documenting the plan as a Gantt chart
- 3 things to know
- A2 Unit 2
Overview
Laying tasks against a timeline, showing durations, dependencies and milestones, marking progress against today's date, and what the chart shows about a project that is running late.
What you need to know
Answer each one before you reveal it.
How are dependencies shown on a Gantt chart?
How is progress recorded on a Gantt chart while the development is under way?
Questions from this subtopic
Each one with the model answer underneath.
- 1
What does the horizontal bar for a task on a Gantt chart tell you?
Model answer
The bar shows the start date, the finish date and therefore the duration of that task.
- 2
How are dependencies shown on a Gantt chart?
Model answer
An arrow runs from the end of one bar to the start of the bar that depends on it.
- 3
How is progress recorded on a Gantt chart while the development is under way?
Model answer
Part of each bar is shaded to show the proportion of that task already completed.
- 4
What does a vertical today line on a Gantt chart tell the developer?
Model answer
The today line marks the current date, so any bar to its left that is not fully shaded is running late.
- 5
Why is a Gantt chart the usual tool for documenting the plan for a desktop development?
Model answer
A Gantt chart shows the tasks, their order, their overlap and the total elapsed time together on one page.
- 6
Why does a Gantt chart alone fail to show which delays matter most?
Model answer
A Gantt chart does not mark spare time on each task, so the chart does not reveal which slipping task moves the delivery date.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Project Management and the Systems Approach in Practice, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.