CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Managing Projects
Monitoring and controlling progress
- 3 things to know
- A2 Unit 1
Overview
Difference between monitoring a project and controlling it, exception report and issue log.
What you need to know
Answer each one before you reveal it.
How does a manager tell the difference between an activity that is late and a plan that was wrong?
What is the difference between monitoring a project and controlling it?
Questions from this subtopic
Each one with the model answer underneath.
- 1
What is the difference between monitoring a project and controlling it?
Model answer
Monitoring is collecting information about what has actually happened, while controlling is taking action on that information, such as re-planning, moving resources or reducing scope.
- 2
Name three sources of information a manager uses to judge real progress.
Model answer
Timesheets showing effort actually spent, completed deliverables that can be inspected, and checkpoint reports from team leaders are three sources of information about real progress.
- 3
Why is percentage complete an unreliable measure of progress?
Model answer
Percentage complete relies on a guess about the work remaining rather than on anything observable, so an activity can be reported as ninety per cent finished for weeks. Completed deliverables and passed milestones are far harder to misjudge.
- 4
What is an exception report?
Model answer
An exception report is raised when a part of the project moves outside agreed limits of time or cost, so that senior management is asked to act only when something genuinely needs a decision.
- 5
What is slippage?
Model answer
Slippage is the difference between the planned date for an activity or milestone and the date now forecast or actually achieved.
- 6
Two weeks into a ten-week stage, 30 per cent of the effort has been spent and 15 per cent of the work is done. What does that suggest?
Model answer
Spending 30 per cent of the effort for 15 per cent of the work suggests the stage was underestimated by roughly a factor of two, so the forecast should be revised immediately rather than waiting for the trend to be confirmed.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Managing Projects, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.