Project Management and the Systems Approach in Practice

Working out the critical path and float

  • 3 things to know
  • A2 Unit 2

Overview

Finding the longest chain of dependent tasks, what total float and free float each mean, why a task on the critical path has none, and what happens when a task overruns its float.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

How is the critical path through a project plan identified?

Key term

A plan has two chains between the same two points, one of 20 days and one of 14 days. Which chain is critical?

Key term

What does it mean to say a task has zero float?

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    How is the critical path through a project plan identified?

    Model answer

    The critical path is the longest chain of dependent tasks through the plan. Its length sets the earliest possible finish date.

  2. 2

    A plan has two chains between the same two points, one of 20 days and one of 14 days. Which chain is critical?

    Model answer

    The chain of 20 days is critical, because the development cannot finish before its longest chain of dependent work is complete.

  3. 3

    A critical chain runs for 20 days and a parallel chain between the same points runs for 14 days. How much float has the shorter chain?

    Model answer

    The shorter chain has six days of float, because 20 days minus 14 days leaves six spare days.

  4. 4

    What does it mean to say a task has zero float?

    Model answer

    A task with zero float cannot slip by even one day without delaying the finish of the whole development.

  5. 5

    Why does the developer watch the tasks on the critical path most closely?

    Model answer

    Delay to a critical task delays the delivery date, while delay elsewhere may be absorbed by the float on that task.

  6. 6

    What happens to the critical path when a task overruns more than its float?

    Model answer

    The overrunning task becomes critical, and the critical path shifts onto the chain that contains it.

Other ways to work this

The same content, four other ways.

What is inside Levo

Six ways to work the same material.

1Closed book
2Open book
3Closed book

The 3-step method, run for you

Answer cold, learn it, then prove it stuck. Levo tracks the jump between your first attempt and your last.

Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures

Cram a whole paper in one sitting

Sort every topic into what you know and what you do not, then drill only the weak ones.

A null is the of one.
absencepresencetype

Blank Blitz makes facts automatic

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

AA null means no value has been recorded.
BZero and an empty string are values.
CA null is the absence of a value.

Build It gets the exam shape right

Assemble a full-mark answer from its marking points, in the order an examiner wants them.

An error is the mistake a person made.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The traps are the mistakes students actually make.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Project Management and the Systems Approach in Practice, on a schedule.

Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.