CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Project Management and the Systems Approach in Practice
Estimating durations, effort and dependencies
- 3 things to know
- A2 Unit 2
Overview
Difference between the effort a task needs and its duration, dependency between two tasks and genuine dependency inside a database-driven solution.
What you need to know
Answer each one before you reveal it.
A task needs 12 hours of work and the developer can give it 3 hours a day. What duration should go in the plan?
Why do estimates for a first development usually turn out to be too short?
Questions from this subtopic
Each one with the model answer underneath.
- 1
What is the difference between the effort a task needs and its duration?
Model answer
Effort is the number of working hours the task consumes. Duration is the elapsed time between the task starting and finishing.
- 2
A task needs 12 hours of work and the developer can give it 3 hours a day. What duration should go in the plan?
Model answer
The duration is four days, because 12 hours divided by 3 hours a day gives four days.
- 3
Why do estimates for a first development usually turn out to be too short?
Model answer
A first estimate counts the coding and forgets testing, correcting faults, writing documentation and waiting for the user.
- 4
How can an estimate be made more reliable?
Model answer
An estimate improves when the task is small, when similar work has been timed before, and when a contingency allowance is added.
- 5
Define a dependency between two tasks.
Model answer
A dependency means one task cannot start or finish until another task has reached a stated point.
- 6
Give an example of a genuine dependency inside a database-driven solution.
Model answer
The data entry form cannot be tested until the tables it writes to have been created.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Project Management and the Systems Approach in Practice, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.