Project Management and the Systems Approach in Practice

Estimating durations, effort and dependencies

  • 3 things to know
  • A2 Unit 2

Overview

Difference between the effort a task needs and its duration, dependency between two tasks and genuine dependency inside a database-driven solution.

What you need to know

Answer each one before you reveal it.

Your recallNot started
Key term

What is the difference between the effort a task needs and its duration?

Key term

A task needs 12 hours of work and the developer can give it 3 hours a day. What duration should go in the plan?

Key term

Why do estimates for a first development usually turn out to be too short?

Questions from this subtopic

Each one with the model answer underneath.

  1. 1

    What is the difference between the effort a task needs and its duration?

    Model answer

    Effort is the number of working hours the task consumes. Duration is the elapsed time between the task starting and finishing.

  2. 2

    A task needs 12 hours of work and the developer can give it 3 hours a day. What duration should go in the plan?

    Model answer

    The duration is four days, because 12 hours divided by 3 hours a day gives four days.

  3. 3

    Why do estimates for a first development usually turn out to be too short?

    Model answer

    A first estimate counts the coding and forgets testing, correcting faults, writing documentation and waiting for the user.

  4. 4

    How can an estimate be made more reliable?

    Model answer

    An estimate improves when the task is small, when similar work has been timed before, and when a contingency allowance is added.

  5. 5

    Define a dependency between two tasks.

    Model answer

    A dependency means one task cannot start or finish until another task has reached a stated point.

  6. 6

    Give an example of a genuine dependency inside a database-driven solution.

    Model answer

    The data entry form cannot be tested until the tables it writes to have been created.

Other ways to work this

The same content, four other ways.

What is inside Levo

Six ways to work the same material.

1Closed book
2Open book
3Closed book

The 3-step method, run for you

Answer cold, learn it, then prove it stuck. Levo tracks the jump between your first attempt and your last.

Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures

Cram a whole paper in one sitting

Sort every topic into what you know and what you do not, then drill only the weak ones.

A null is the of one.
absencepresencetype

Blank Blitz makes facts automatic

Rapid timed gap-fills on the terms and numbers you need to recall without thinking.

AA null means no value has been recorded.
BZero and an empty string are values.
CA null is the absence of a value.

Build It gets the exam shape right

Assemble a full-mark answer from its marking points, in the order an examiner wants them.

An error is the mistake a person made.
TrueFalse

Test It catches misconceptions

Spot the fault in a statement. The traps are the mistakes students actually make.

721941163128510

Brain Breaks between sessions

Short focus games to reset attention, so the next set lands better than the last.

Every question in Project Management and the Systems Approach in Practice, on a schedule.

Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.

Or £46 a year, about £3.83 a month. Cancel anytime.