CCEA A-Level Software Systems Development CL4
Software and the Development Environment
Defining Data: Types, Variables and Classes
Program Control Structures
Objects, Classes and Data Structures
Exception Handling and Managing Input and Output
Testing an Object Oriented Application
Graphical User Interface Objects and Events
Multiple Forms and Linking to Files
Designing, Testing and Evaluating an Event Driven Application
Reasons for Systems Development and Systems Methodologies
Managing Projects
Testing Strategies
Database Concepts and Entity Relationship Modelling
Normalisation and Structured Query Language
Project Management and the Systems Approach in Practice
Defining Requirements and Documenting the Design
Building a Desktop Solution with a Database
Testing and Evaluating the Solution
Testing and Evaluating the Solution
Evaluating delivery against the project plan
- 3 things to know
- A2 Unit 2
Overview
Comparing what was delivered with what was scheduled, where the estimates were wrong and why, what was dropped or deferred, and what the variance says for the next plan.
What you need to know
Answer each one before you reveal it.
Which figure shows most clearly whether the plan was realistic?
How should slippage be reported in an evaluation?
Questions from this subtopic
Each one with the model answer underneath.
- 1
Explain what evaluating the development against the project plan involves.
Model answer
The evaluation compares the actual dates, durations and order of the work with the plan that was agreed and updated.
- 2
Which figure shows most clearly whether the plan was realistic?
Model answer
The difference between the estimated and the actual duration of each task shows most clearly whether the plan was realistic.
- 3
How should slippage be reported in an evaluation?
Model answer
Slippage is reported with the task affected, the size of the delay, its cause, and its effect on the tasks that followed.
- 4
Why is the cause of a delay more useful than the fact of it?
Model answer
The cause is what can be avoided next time, while the delay on its own teaches nothing.
- 5
What does it mean if every stage overran by roughly the same proportion?
Model answer
A consistent overrun points to an optimistic estimating method rather than to any single task going wrong.
- 6
How is the chosen approach judged once the solution has been delivered?
Model answer
The approach is judged on whether it kept the work under control, absorbed the changes that arose and delivered on time.
Other ways to work this
The same content, four other ways.
What is inside Levo
Six ways to work the same material.
Every question in Testing and Evaluating the Solution, on a schedule.
Attempt a question from memory, write the correct version, then attempt it again. Levo records the jump between your first attempt and your last, and brings each question back on the day you are due to forget it.
Or £46 a year, about £3.83 a month. Cancel anytime.